Construction activity centered on cellar-level structural framing, featuring cold-formed steel floor joist assembly over the cellar space and masonry pointing along stone foundation walls.
Crews positioned web-perforated cold-formed steel floor joists across the cellar, setting members into foundation pockets and fastening transverse track bridging to lock joist spacing. Masonry workers packed mortar grout around steel bearing ends where joists seat directly into stone foundation walls, while site workers cleared demolition debris and managed material staging outdoors.