Construction Update
All Updates

Interior Metal Stud Framing and Wall Layout

July 27, 2026

Site progress shifted toward interior partition construction and perimeter wall track installation across the newly decked floor.

Crews measured layout lines directly on the plywood subfloor before cutting metal tracks and studs to size using chop saws and angle grinders. Carpenters secured the bottom tracks into the deck and erected vertical light-gauge steel studs along the brick walls, fastening them at the top floor joists to build out interior partition framing. Supervisors reviewed site blueprints to verify door rough openings and wall placement.