Onsite activity targeted securing the structural deck and finalizing steel joist connections across the floor opening.

Workers installed subfloor plywood panels directly over the newly placed steel joists, driving fasteners flush to secure the subfloor plane. Concurrently, tradespeople used angle grinders to make precision cuts on light-gauge steel members and mixed sand/topping mortar onsite to prepare bearing pads and fill wall gaps along the exposed brick.